 Construction preliminary schedule set
(updated March 2006)

Planning for the district's $94.5 million construction project is in full swing, with construction slated to start in spring 2007.

Construction will be in phases, with all work scheduled to be completed by 2010. The preliminary schedule is:

graphic bullet Spring 2007: Construction begins at Niskayuna High School, Van Antwerp Middle School, Craig and Glencliff elementary schools. Classroom technology and digital heating controls also added districtwide.

graphic bullet Spring 2008: Construction begins on Hillside and Rosendale elementary schools.

graphic bullet Fall 2008: New classrooms and renovations complete at Craig and Glencliff.

graphic bullet Spring 2009: Birchwood Elementary School construction and Iroquois Middle School renovations begin.

graphic bullet Fall 2009: New classrooms and renovations complete at Hillside and Rosendale.

graphic bullet Fall 2010: Birchwood, Iroquois and high school work complete.